POWER SHUTOFFS IN ALL RESIDENTIAL UNITS
The installation of new sub-metering system that will allow the Association to bill back electricity based on actual consumption to each unit is underway. In order to connect equipment to each unit’s electrical system, the project now requires power shutoff on each floor during one day from 10:00 AM – 2:00 PM. Please review below schedule. Power will be restored each day as soon as work is completed, which may be before 2:00 PM.
Every effort will be made to restore power as soon as possible.
During power shutoff hours, residential units on affected floor won’t have electricity, including interruption of internet services. If you refrain from opening the refrigerator door, temperature inside the refrigerator should not fluctuate. We recommend charging your electronic devices in advance. Also, shut down computers without a backup power source before the power is interrupted.
The fire life safety systems will continue to operate during power shut off. Lights in common area corridors will remain operational and elevators will continue to function normally. If necessary, amenities on the rooftop level will be available during each power shut off.
To download a copy of the schedule, please Click Here
Floor
|
Date
|
Floor
|
Date
|
Townhome & Penthouse units
|
Monday, April 16, 2018
|
12th
|
Monday, April 30, 2018
|
21st
|
Tuesday, April 17, 2018
|
11th
|
Tuesday, May 01, 2018
|
20th
|
Wednesday, April 18, 2018
|
10th
|
Wednesday, May 02, 26, 2018
|
19th
|
Thursday, April 19, 2018
|
9th
|
Thursday, May 03,, 2018
|
18th
|
Friday, April 20, 2018
|
8th
|
Friday, May 04, 2018
|
17th
|
Monday, April 23, 2018
|
7th
|
Monday, May 07, 2018
|
16th
|
Tuesday, April 24, 2018
|
6th
|
Tuesday, May 08, 2018
|
15th
|
Wednesdays, April 25, 2018
|
5th
|
Wednesday, May 09, 2018
|
14th
|
Thursday, April 26, 2018
|
4th
|
Thursday, May 10, 2018
|
13th
|
Friday, April 27, 2018
|
3rd
|
Friday, May 11, 2018
|
WINDOW CLEANING UPDATES
Washing all exterior windows and balcony glass is underway, scheduled to end on Friday, May 4th, 2018. Work hours shall be between 8:00 AM and 5:00 PM, Monday through Friday. The drop schedule is below. Workers will be utilizing the swing stage along the outside of the building.
Please be mindful of the following:
- You may want to close your window coverings for privacy
- For some units, not all windows may be cleaned on the same day due to the configuration of the building exterior.
- Due to wet conditions, please exercise caution when walking around the building’s perimeter. Signs will be posted in the areas where work is taking place.
- Please keep all windows and sliding doors closed when window cleaning is in your area.
- Please be sure to remove all items or furniture from balconies that you may not want to get wet. Staff will not move any items on any balcony.
Balcony/Patio – Glass & Exterior Panels
For units with balconies and patios, cleaning of balcony glass and exterior surfaces (excluding floor) is also included with this service at no additional charge. Balcony cleaning is scheduled to take place April 25 to May 4. The schedule will be available by April 6.
Schedule:
South Side – building section facing 12th Street – COMPLETED
West Side – building section facing back alley/Hope Street – COMPLETED
Floors 6 to 23
North Side – building section facing Elleven & Luma buildings/11th Street – April 5, 6, 9 & 10
East Side – building section facing Grand Avenue – April 11, 12, 13, 16, 17 & 18
Floors 6 to 23
East (Grand Ave) and West (back alley) sides – April 23, 24 & 25
Floors 1 to 5 Units covered separately because of necessary boom lift instead of swing stage to access cleaning areas
|