We’ve been informed about renovations taking place on the Luma and Elleven pool deck. Here is the complete work schedule along with further details.
The Boards of Luma and Elleven have contracted with Downtown Pools to undertake a comprehensive renovation of the pool and spa. Starting on Monday, April 1st, the project is expected to span approximately 60 days. The pool area will be closed during this entire time. Below is an estimated schedule of the process and what to expect as the project progresses.
Weeks 1-2: Draining and Demolition
The existing deck, pool, and spa tiles will be demolished during these weeks. Heavy to medium noise levels and light dust exposure can be expected.
Weeks 3-4: Surface Preparation and Deck Installation
Surfaces will be prepared for new materials, and a new slate deck will be installed. Expect medium noise levels and light dust exposure during this phase.
Weeks 5-6: Pool and Spa Tiling
New tile will be installed in the pool and spa interiors. Minor noise levels can be anticipated during the tiling process.
Weeks 7-8: Project Completion and Final Inspection
The final clean-up and inspection visits will occur during these weeks. No significant noise or dust is expected.
The estimated project completion date is June 15th, 2024.